Welcome To The WestSeattleHerald.com Updated As Warranted

Local News




California Avenue paving to finish by mid-August

Tuesday, June 19, 2007

Work on California Avenue between Southwest Genesee and Southwest Spokane Street has been completed except pavement striping, to be done within the next three weeks.

Final paving of California Avenue between Spokane Street and Admiral Way is tentatively scheduled for the last week of June.

The contractor plans to begin work on SW Admiral Way between 41st Avenue SW and SW Olga Street the first week of July.

The entire project is scheduled for completion in mid-August.

Normal work hours for the contractor on California Avenue are 7 a.m. to 5 p.m. Monday through Friday.

During the peak periods (6-9 a.m. and 4-6 p.m.) at least one lane of traffic in each direction on California Avenue will remain open. At other times, traffic on California may be restricted to one lane with the use of flaggers. Turns to and from side streets to California Avenue may be restricted. Detours may be necessary at times.

On-street parking is not allowed in the construction area.


Please share your point of view on this story. Comments posted with First and Last names will be considered for publication in the print edition. You may request that your name not be published. You may also send your comment directly to the editor at wseditor@robinsonnews.com.


(optional)
   
printable version e-mail this story


This Week's Headlines
Stories with Video
WXPort

West Seattle
Traffic Cams
Bridge at I-5 Bridge at 35th
Fauntleroy & Alaska

Sponsored Links